Legacy the School of Sport Sciences

Bastrop, TX

Legacy the School of Sport Sciences

The development and construction of a charter school facility including associated football and
baseball fields and basketball courts. During the pre-construction phase, LoneStar performed constructability reviews and value engineering to save the client nearly 10% of construction costs. The school buildings will ultimately be approximately 52,989 square feet and will have a capacity of 625 students. The scope of work will be conducted in the following three phases:
1. Phase I – Renovation of the existing office building to provide 20 traditional classrooms, two
science labs, administrative offices, and a football field for a capacity of 550 students.
2. Phase II – Construction of an outdoor baseball field – complete 90 days after CenterPoint Energy
relocates or removes their easement and removes their power poles
3. Phase III – Construction of a 25,379 square foot building and sports facility that will consist of 2
adjacent basketball courts, a dining area, 4 additional classrooms and laboratory spaces, and
additional restrooms. This addition will increase school capacity to 625 students.

Client: EPR Properties
Location: Spring, TX
Completed: December 2018
Delivery Method: Design/Build
Services: Design-build,
General Construction, Pre-Construction, Commercial Development
Awards: 2014 Mid-West Steel Building Company,
Building of the Year
+ Project Details
Client: EPR Properties
Location: Spring, TX
Completed: December 2018
Delivery Method: Design/Build
Services: Design-build,
General Construction, Pre-Construction, Commercial Development
Awards: 2014 Mid-West Steel Building Company,
Building of the Year
Legacy the School of Sport Sciences